What can I do with the Gantt View?

Paul Hoemke
Paul Hoemke
  • Updated

What can I do with the Gantt View?
autoscheduled_Gantt_up_close_2022-03-01.png

  • You can set planned start dates and due datesitem_status_and_dates.png
  • You can update the item’s status (Open, In Progress, Complete, Verified)
  • You can set the responsible person 
  • You can link items with predecessors and successors using standard dependencies:
    • “Finish to Start” - target task can’t start before the source task ends (but may start later)
    • “Start to Start” - target task can’t start until the source task starts (but may start later)
    • “Finish to Finish” - target task can’t end before the source task ends (but may end later)
    • “Start to Finish” - target task can’t end before the source task starts (but may end later)
      linking_end_to_start.png finish_to_finish_linked.png
  • You can use Auto-Scheduling to control planned start and finish dates
    • NOTE: If you use Gantt view to auto-schedule, you must change dates in the Gantt View to apply auto-scheduling to successor and predecessor items 
  • You can mark the progress of an item (percent complete)
  • You can export a snapshot of the Gantt View to PDF or to Excel

Was this article helpful?

0 out of 0 found this helpful

Have more questions? Submit a request